Committee on Anti-Dumping Practices - Committee on Subsidies and Countervailing Measures - Committee on Safeguards - Note from the Secretariat

NOTE FROM THE SECRETARIAT

In order to assist Members, the following are deadlines for submission of various documentation following up on the April 2025 regular meetings, and in conjunction with the October 2025 regular meetings of the Committees on Anti-Dumping Practices, Subsidies and Countervailing Measures, and Safeguards, which will be held in the week of 27 October 2025.

Members are reminded to always submit written questions and answers directly to the Member concerned at the same time that they submit them to the Secretariat for circulation.

1.  _    AD/CVD/SG LEGISLATION NOTIFICATIONS

The Secretariat will circulate to Members by 19 September 2025 the annotated draft agenda in which a list of the new notifications of legislation, that will be on the agenda for review at the regular meetings in October 2025, will be reflected. Pursuant to procedures adopted by the Committees[1],[2], notifications circulated in all three WTO working languages not later than 15 September 2025 will be reviewed at the relevant Committee's October 2025 regular meeting.

1.1  Deadlines for submission of questions and answers following up on the April 2025 regular meetings:

23 May 2025                     Written follow-up to questions posed orally at the April 2025 regular meetings regarding notifications of legislation reviewed at those meetings.

13 June 2025                    Written answers to all written questions (those posed in writing prior to the regular meetings by the deadline of 7 April 2025 and those posed orally at the meetings and followed-up in writing after the regular meetings by the above deadline of 23 May 2025) regarding notifications of legislation reviewed at the Committees' regular meetings in April 2025.

1.2  Deadlines for submission of questions and answers in conjunction with the October 2025 regular meetings:

15 September 2025         Written questions regarding previously-reviewed notifications of legislation, for consideration at the Committees' regular meetings in October 2025.

6 October 2025                Written questions regarding new notifications of legislation to be reviewed at the Committees' regular meetings in October 2025. Such questions would be answered orally at the October 2025 regular meetings and subsequently followed by written answers to be submitted by the deadline indicated by the Chairs at those meetings and reflected in the next "Note from the Secretariat" to be issued after the meetings.

13 October 2025              Written answers to written questions submitted by 15 September 2025 regarding previously-reviewed notifications of legislation, for consideration at the Committees' regular meetings in October 2025.

2.  _      Subsidy Notifications

2.1  New and Full Subsidy Notifications

2025 new and full notifications are due on 30 June 2025. Pursuant to the procedures adopted by the Committee at its April 2005 regular meeting and circulated in document _G/SCM/117[3], only notifications circulated in all three WTO working languages not later than 1 July 2025 may be reviewed at the special meeting that will be held in October 2025. The Secretariat will circulate to Members, shortly after, a list of 2025 new and full subsidy notifications, and any other new and full notifications not previously reviewed, that will be on the agenda for review at that meeting.

29 July 2025                     (a) Written questions regarding 2025 subsidy notifications, and other subsidy notifications not previously-reviewed, scheduled for review at the Committee's October 2025 special meeting.

                                           (b) Written follow-up or other questions concerning subsidy notifications previously reviewed, including those reviewed at the Committee's April 2025 special meeting or at any earlier meetings.

30 September 2025         (a) Written answers to written questions regarding 2025 new and full subsidy notifications, and other new and full notifications not previously‑reviewed, scheduled for review at the Committee's October 2025 special meeting.

                                           (b) Written answers to any follow-up or other questions concerning previously reviewed subsidy notifications (including those discussed at the Committee’s April 2025 special meeting or any earlier meetings).

2.2  Transparency Notifications Relating to Article 27.4 Export Subsidy Phase-Out Period

The Members with Article 27.4 extensions are required, pursuant to paragraph 2(c) of the procedures in _WT/L/691, to provide transparency notifications in respect of 2015, the last of the two final years for phasing out the export subsidies. These notifications were due on 30 June 2016.

__________



[1] _G/ADP/W/284/Rev.1 – _G/SCM/W/293/Rev.1.

[2] _G/SG/W/116.

[3] At its regular meeting held on 29 April 2025, the Committee agreed that the procedures contained in _G/SCM/117 would apply to the review of the 2025 new and full subsidy notifications.